ENGINEERING GUIDE

Specifying Secure Remote Access for Water Operations

Define remote water access roles, connection boundaries, session records and outage tests before selecting a monitoring or operations platform.

Browse technical guides ↗
Specifying Secure Remote Access for Water Operations
HOSON water site illustration used for remote operations planning. Access methods, user privileges and installed software must be confirmed for each proposed project.

How should remote access to a water system be specified?

Specify remote water access as an approved set of tasks, users, connection paths and recorded actions. Identify what each person needs to view or change, which equipment they may reach and who can authorize a session. Define how access is disabled and how local operation behaves when communications are lost. A product demonstration should then prove the proposed permissions and failure behavior. A general statement that a platform offers secure access does not provide enough detail to approve a connection to a working treatment system.

Remote monitoring, remote assistance and remote control create different operational responsibilities. A central operator reading a trend has a different task from a technician changing a controller program. Keep those tasks explicit in the enquiry and assess each proposed path with the owner’s controls and cybersecurity staff. HOSON’s smart water overview describes authorized remote diagnosis and support. The following specification approach helps a purchaser confirm the precise functions, infrastructure and service responsibilities included in the proposed configuration. It does not assume a particular software package or hosting model.

Start with a task and authority matrix

Write down the tasks that motivate remote access. Typical procurement questions include whether a central operator needs current measurements, whether a maintenance specialist needs to retrieve diagnostics, and whether any remote user needs permission to change settings. For each task, identify the asset, authorized role, approving person and expected record. State whether the task can be completed through exported information or requires an interactive session. Review this matrix with the person accountable for plant operation so that a convenient support route does not silently become an operating authority.

Define the handoff between remote and local personnel. If a remote specialist suggests a setting change, decide who confirms the plant is ready and who carries it out. Where remote control is requested, describe any required local authorization and how control responsibility is made visible. These details belong in the project operating procedure and acceptance plan. Keep emergency actions and process protections under the owner’s approved control philosophy. The supplier should explain how the proposed remote arrangement interacts with that philosophy before the owner agrees to the connection.

TaskAuthority to defineAcceptance evidence
View status and trendsSites and data visible to the named roleA permitted site opens and an unassigned site is denied
Provide maintenance assistanceApproved session, target asset and durationAuthorization and session records match the task
Acknowledge an eventWhether acknowledgment is permitted remotelyActor and time are retained without changing the process
Change a settingApprover, permitted value range and local coordinationAn approved test follows the operating procedure
Maintain usersAccount owner and removal responsibilityExpired access no longer reaches the system

Map every proposed route into the plant

Request a connection drawing that follows the path from the remote person or service to the intended plant asset. Include the service boundary, gateway, network zones and equipment reached. Record who owns each component and who maintains its configuration. Review temporary arrangements as carefully as permanent ones. A commissioning laptop, a vendor modem or an emergency support tool can create a route that is absent from the final drawing. Ask the integrator to identify how those paths are removed or incorporated into the approved design at handover.

CISA’s July 2026 water sector bulletin calls for removing publicly exposed PLCs from the internet and recommends approved intermediary access arrangements. It also identifies undocumented cellular connections as an exposure that owners should examine. For procurement, ask the supplier to show the proposed boundary and explain how it avoids direct public access to controllers. Have the owner’s qualified network team verify the implemented path using an approved method. The objective is a documented and reviewed architecture, including existing connections that the new project will depend on.

Make identity, approval and expiry reviewable

Use a user register that identifies the employer, business purpose, approving owner and sites assigned to each account. Define the start and end of contractor access and the event that triggers removal, such as completion of a support task or a change of role. Ask how the solution handles a shared workstation without losing individual accountability. When an organization account is used by a service, document its owner and intended function separately from human access. A periodic review should be possible from an export or a maintained register.

Specify the authentication method for each remote path, including the owner’s requirement for multifactor authentication. Confirm how enrollment, lost authentication devices and recovery are handled. Recovery should go through an approved owner process that can be demonstrated without exposing production credentials. NIST’s 2026 water sector discussion describes layered technical and administrative controls for remote access, including identity checks, role permissions and access records. Translate those concepts into evidence the proposed supplier can show, rather than accepting a security feature name without an explanation of its use.

Limit permissions to the work being performed

Design test accounts around the agreed tasks. A viewer should see the required site information and receive a clear denial when attempting an unassigned function. An engineer’s access should be constrained to the assets and tools needed for the approved work. Ask whether access to one site permits movement to another site or to other network equipment. Where the proposal cannot provide the desired separation, record the limitation and have the owner decide whether a different architecture or working procedure is required before activation.

Review both the screen permissions and the underlying connection. Hiding a button is insufficient evidence that the associated operation is restricted. During acceptance, use a controlled test environment or an owner-approved demonstration to verify denied operations. Record the result and the tested version. Keep administrative activities separate from routine monitoring responsibilities where the approved design supports this distinction. The permission matrix should also identify who can change permissions themselves. This makes later staff changes manageable and gives auditors a coherent account of why a person could reach an asset.

Water-treatment equipment and field operations context
Water system illustration for discussing access boundaries and monitoring tasks. It is not a screenshot of a deployed access console or proof of any cybersecurity control.

Agree on the records needed after a session

Specify what the owner must be able to reconstruct after remote work. A useful session record identifies the user, target, approval reference, start and end times, and outcome. For configuration work, also retain the approved change, the applicable version or backup reference, the action taken and the person who verified restoration. Determine whether these records come from the platform, the access service or the project’s work management procedure. If the technical system does not capture a needed detail, agree on a practical manual record and its owner.

Define who can review and export the records, how long they are retained, and what happens when a service contract ends. Use a sample export in acceptance so that the owner can check time references and interpret the fields. Consider the sensitivity of plant information when deciding where records are stored and who receives them. A supplier may need diagnostic evidence for a support request, but the approved scope should identify the information shared. Keep maintenance usefulness and appropriate information handling visible in the same review.

Test loss of communications and loss of access

Write a failure scenario for the connection and another for the user’s access. During a controlled test, interrupt the approved communication path and confirm the expected local operating state. Check the remote display’s age and quality indication, and record whether historical data is retained as proposed. Restore the connection and inspect the event order and current equipment state. The owner should define how to handle any pending request or interrupted change. Do not assume that reconnection should repeat a command that was issued before the interruption.

Separately, revoke a test user and confirm the person cannot begin another session. Ask what happens to an existing session and how rapidly the chosen revocation method takes effect. Test the approved method to disable remote access while local staff retain the access needed for plant operation. Record which role can make that decision and how the access service is restored after review. These exercises expose dependencies that an ordinary product tour may miss, including the need for an external identity service or an administrator located away from the site.

Include maintenance and incident responsibilities in handover

Assign responsibility for the remote access components throughout their service life. Record who receives vendor notices, assesses an update, schedules a maintenance window, keeps backups and confirms the system operates correctly afterward. The controls team should assess changes against plant availability and process requirements. Include access equipment and software in the owner’s maintained inventory. EPA’s OT assessment recognizes that even occasionally connected equipment may fall within the operational technology scope, so a device used only for support still deserves an identified owner and approved procedure.

Prepare a contact and escalation sheet for suspicious activity or unexpected configuration changes. Local staff need a clear first reporting route, a way to preserve relevant records and an approved means to request isolation of remote access. Coordinate this with the owner’s incident response arrangements. During a tabletop exercise, ask who is available outside office hours and how they know which supplier to contact. The purpose is to confirm responsibilities and access to information. The exercise can be completed without generating a real incident or testing disruptive actions against a live process.

Compare proposals using the same evidence package

Send each bidder the task matrix, site connection constraints and required acceptance scenarios. Request a completed architecture drawing, permission matrix, account lifecycle procedure, session record example, maintenance scope and handover list. Identify any recurring licenses, connectivity charges or third-party services required for the offered arrangement. Ask what functionality remains available if a subscription ends or the owner changes its support contractor. Those answers make the operating implications of different proposals easier to compare alongside the quoted equipment and implementation costs.

For a HOSON enquiry, explain whether the initial requirement is monitoring, expert assistance or an owner-approved control function. Provide the existing controller and network information through the project’s approved information-sharing route. Ask HOSON and the owner’s integrator to identify which functions they propose, how they would be verified and who would support them. Accept the remote connection only after the responsible teams have reviewed the evidence and closed the agreed findings. Revisit the specification when the site, user group or operating authority changes.